|
By Moneth
G. Deposa
Variety News Staff
FROM an original
estimate of $5.6 million, Tinians wastewater project is now projected
to cost over $26 million, according to the islands officials.
In a letter to Gov. Benigno R. Fitial, Tinian officials said that when
the study for the project was prepared, the consultant recommended an
outfall system and a site different from what the Commonwealth Utilities
Corp. recommended.
They said the change in the system and site resulted in an increase in
the projects cost.
Local officials said although the need for a wastewater system still exists,
the dynamics of the current local economy does not make the system
feasible nor require such urgency in construction.
They added, In fact, since the proposed new hotel-casinos will be
constructing their own wastewater processing systems, their projects are
not contingent on the availability of a municipal wastewater system.
Due to the increased cost and unavailability of funding, they said, the
project cannot commence at this time.
Tinian leaders want the U.S. Interior Departments Office of Insular
Affairs to reprogram the projects federal funds so they can be used
for the island airports instrument landing system instead.
OIA said it is the governor who should make the request.
With the current project estimates of $17 million for the first
phase of the wastewater project and over $26 million for the entire project,
it would take several years of earmarking the entire annual share of Tinians
CIP funds to increase the currently earmarked funding of $11.1 million
to a sufficient level for construction to begin, the Tinian officials
said in aletter to the governor.
They said it is best to use the funding for other priority projects like
the instrument landing system.
They said they will replenish the funds through future federal capital
improvement monies and revenues to be generated from the new casinos.
The Tinian officials are asking the governor to ask for the reprogramming
of the wastewater project funds.
|