|
By Haidee V.
Eugenio
Variety Assistant Editor
THE Water Task Forces
installation of 7,000 water meters on Saipan delayed by a year
due to a procurement protest and appeal may now be able to proceed.
Yesterday, Public Auditor Mike Sablan upheld the decision of Procurement
and Supply Director Herman Sablan to deny Reaction Co.s protest
on the cancellation of the original invitation for bid 06-GOV-003 and
the subsequent solicitation for the installation of the water meters through
IFB 06-GOV-097.
If Reaction Co. does not file a request for reconsideration of OPAs
decision, then the procurement may continue.
Reaction Co., which had the lowest bid of some $700,000, wants to be awarded
the contract under the original IFB, and asked the Office of the Public
Auditor to cancel the second IFB, among other things, in an appeal filed
on Dec. 28, 2006.
The public auditor, in an eight-page appeal decision, said the cancellation
of the first IFB was allowable under CNMI Procurement Regulations, and
that OPA finds no compelling reason to justify the cancellation of the
second IFB.
Reactions appeal, therefore, is denied, said OPAs
Sablan.
Any interested party, however, may request reconsideration of a decision
by the public auditor and such request must be received by OPA not later
than 10 days after the date of the April 2 decision.
Noel M. Tolentino, general manager of Reaction Co., yesterday told Variety
via telephone that they are still reviewing OPAs appeal decision
and have yet to decide whether to ask for a reconsideration of OPAs
appeal decision.
Reaction Co. was notified by the Water Task Force on March 20, 2006 that
it would be awarded the contract. But the task force later asked for the
cancellation of the original IFB, saying that it no longer requires
the services being procured.
The Water Task Force also said that continuing the metering of water
service should be delayed until the Commonwealth Utilities Corp. has registered
and initiated billing of the meters recently installed by the task force,
and identified and resolved any problems with the new type of meters used
in the project.
The Procurement and Supply Division granted the IFB cancellation request.
The public auditor said a cancellation of procurement after bid opening
is a serious matter as bidders, with knowledge of the prior bids, could
potentially have an unfair advantage if later permitted to compete again
for the same procurement.
Instances, however, do exist when cancellation is appropriate and
allowable, said OPAs Sablan, when such action is determined
in writing by the official with expenditure authority and approved by
the director of the Procurement and Supply Division to be in the best
interests of the government for any of a variety of reasons.
These reasons include inadequate or ambiguous specifications contained
in the solicitation, goods or services being procured which are no longer
required, and cancellation is determined to be in the best interests of
the government.
OPA finds that there was a written determination by the Water Task
Force, which was approved by the director of Procurement and Supply, that
the services under IFB 06-GOV-003 were no longer required and that cancellation
of IFB-06-GOV-003 was in the best interests of the government, said
the public auditor.
He added that the subsequent solicitation for the installation of the
7,000 water meters was issued with several changes in place in the form
of IFB 06-GOV-097.
|