|
By Gina Tabonares
Variety News Staff
DESPITE the penalties that
are expected to reach $1 million in a few months, the government of Guam
remains unperturbed about meeting the Ordot Dump Consent Decree deadlines,
prompting the U.S. Attorneys Office to file a motion yesterday asking
the court to impose a set of court enforced deadlines.
U.S. Attorney for the Districts of Guam and the NMI Lenny Rapadas filed
a motion with the District Court of Guam on behalf of the U.S. Environmental
Protection Agency to enforce the consent decree with Guam for the construction
of a new landfill and the closure of the Ordot Dump.
Rapadas said the federal government filed the motion after the Guam Department
of Public Works failed to complete the design, permitting and construction
of the new landfill and has failed to award a contract for its construction.
According to the U.S. Attorneys Office, DPW also failed to award
a contract to properly and permanently close the Ordot Dump.
Under the February 2004 Consent Decree, GovGuam was required to award
a construction contract for the new landfill by April 21, 2006 while completion
for the closure of Ordot Dump was to be on Oct. 23, 2007.
However, GovGuam failed to comply with the consent decree and failed to
raise the financial resources to comply.
As of Jan. 31, 2007, the USEPA-assessed penalty, at a rate of $5,000 per
day, under the stipulated penalties for missed deadlines to complete the
contract for Ordots closure has reached $839,500.
Last month, the U.S. Attorneys Office and the USEPA brought the
continuing violations of the government of Guam before the court, saying
that the local government, specifically DPW, is unwilling to meet its
obligations and intends to purposely violate the consent decree.
During a status conference with Judge Joaquin Manibusan, lawyers representing
DPW cited lack of funds and the complexity of landfill design, and asked
for at least 21 more months to build a new dump for an estimated $20 million
funding.
Todays action is necessary to ensure the work to build a new
landfill for Guam is completed and the Ordot Dump properly closed to protect
the residents and environment of Guam, said Rapadas.
We are disappointed that GovGuam has fallen short in complying with
the consent decree and the important effort to improve the islands
solid waste disposal. We are asking the court to impose these deadlines,
creating the basic building blocks that will allow GovGuam to eventually
meet its obligations, he added.
In January 2005, the USEPA assessed a $7,250 stipulated penalty on GovGuam
for failing to identify a new landfill site. In early 2006, a fine of
$7,500 was assessed for failing to submit the draft final plan for the
new landfill.
By May 2006, the USEPA had assessed stipulated penalties in the amounts
of $51,500 and $7,000 for failure to submit a draft wetlands mitigation
plan, and to award a contract for the Ordot Dump closure.
Atty. Robert Mullaney earlier told the court that their intention is not
to simply collect fees from GovGuam but to get some options to move forward
and to pressure the local government to prioritize the creation of a new
landfill.
He said for over 10 years, the federal government has been attempting
to solve the problem with the government of Guam and extending the deadline
will resolve the problem.
The U.S. Attorneys Offices motion was a response to the instruction
of Judge Manibusan to submit its proposal on how the court should address
the landfill issue.
Judge Manibusan also told GovGuam lawyers to submit their motion to modify
the deadlines of the consent decree.
Feb. 14, 2007 was the deadline for the federal government to reply to
the motion while local lawyers have until Feb. 21 to respond. A motion
hearing is set for March 8 at 9 a.m.
|