THE first shipment of power transmission and distribution materials arrived Wednesday afternoon at the Commonwealth Utilities Corporation’s warehouse from the Guam Power Authority, with additional materials expected to arrive in the coming weeks to support ongoing power restoration efforts on Saipan and Tinian.

 The initial shipment includes:

35 transformers

45 reels of No. 4 triplex wire

35 reels of No. 2 triplex wire

25 45-foot concrete power poles

28 40-foot concrete power poles

With the additional materials now on hand, crews can continue repairs and replacement of damaged electrical infrastructure on Saipan and Tinian.

CUC extends its appreciation to GPA for its continued support and partnership in island-wide power restoration and recovery efforts.