Feeder 2: 2nd Partial will be turned off from 8 a.m. to 10 a.m., which will affect Beach Road Garapan, Kristo Rai Church, south to San Jose intersection.
Feeder 3: 3rd Partial will be taken offline from 10 a.m. to 12 noon, affecting Gualo Rai intersection, south to Chalan Pale Arnold, and Chalan Monsignor Guerrero Road intersection.
Kiya 2: 2nd Partial is scheduled from 12 noon to 2 p.m. This will affect portions of Koblerville, As Gonno, San Antonio and Afetnas.
From 2 p.m. to 4 p.m., Feeder 4: 2nd Partial will be offline, cutting the power service on Capital Hill, Kagman and portions of Papago, particularly the Botanical Garden area.
The entire grid of Feeder 7 will be affected from 4 p.m. to 6 p.m. Feeder 7 covers the Lower Base industrial area, north to Tanapag, Achugao, San Roque, As Matuis, and Marpi.
The 2nd Partial of Kiya 1 facility will be turned off between 6 p.m. and 8 p.m., affecting the Commonwealth Ports Authority, portions of Koblerville and As Perdido.
Lastly, Kiya 4: 2nd Partial will be taken offline between 8 p.m. and 10 p.m. This will affect electricity at Mount Carmel and portions of Chalan Kanoa.
“Water and wastewater services will also be affected in the respective areas as a result of the power outages,” Camacho said.
He added that CUC will try to keep with the contingency load shedding schedule as long as no other emergencies arise at the power plant or at their field facilities.