Based on the new schedule, Feeder 2: 2nd Partial will be turned off from 8 a.m. to 10 a.m. This will affect Beach Road Garapan, Kristo Rai Church, south to San Jose intersection.
Feeder 3: 3rd Partial will be taken offline from 10 a.m. to 12 noon, affecting Gualo Rai intersection, south to Chalan Pale Arnold, and Chalan Monsignor Guerrero Road intersection.
Kiya 1: 2nd Partial is scheduled from 12 noon to 2 p.m. This will affect portions of Koblerville, As Perdido, the airport, and the Commonwealth Ports Authority.
From 2 p.m. to 4 p.m., Kiya 4: 2nd Partial will be offline, affecting Mount Carmel, south to portions of Chalan Kanoa.
The entire grid of Feeder 7 will also be affected from 4 p.m. to 6 p.m. Feeder 7 covers the Lower Base industrial area, north to Tanapag, Achugao, San Roque, As Matuis, and Marpi.
Feeder 4: 2nd Partial will be turned off between 6 p.m. and 8 p.m., affecting Kagman, Capital Hill, portions of Papago and the Botanical Garden.
Lastly, Kiya 2: 2nd Partial will be taken offline between 8 p.m. and 10 p.m. This will affect As Gonno, San Antonio, Afetnas and portions of Koblerville.
“Water and wastewater services will also be affected in the respective areas as a result of the power outages,” Camacho said.
He added that CUC will try to keep with the contingency load shedding schedule as long as no other emergencies arise at the power plant or their field facilities.