Power Plant 4 has fuel until tomorrow

On Friday, Variety was told,  PP4 was able to receive 92,000 gallons of fuel after the central government released $300,000 to the Commonwealth Utilities Corp.

PP4 is generating an average of 11 megawatts a day for CUC.

A PP4 plant official said they still have 32,000 gallons of undelivered fuel from the Mobil.

Normally, the plant official said PP4’s fuel requirement is 200,000 gallons every week.

Last week, CUC Executive Director Antonio Muna said the $300,000 was only enough to supply the power plants’ fuel needs until Tuesday, June 8.

He said CUC needed $1.4 million in additional funding from the central government.